How to price a job

Pricing a job comes down to five numbers: your time, your materials, your overheads, your margin and a contingency. Here's a method you can use on any job, with a worked example.

On this page
  1. How do you work out your day rate?
  2. How do you price a specific job?
  3. What does a worked example look like?
  4. Should you charge by the hour or a fixed price?
  5. How do you check your price is right?
  6. What should you do after pricing?
  7. How does VAT affect your prices?
  8. Key takeaways
  9. Questions
  10. Sources

To price a job, estimate the hours and multiply by a day or hourly rate that covers your wage and overheads, add materials at cost plus a markup, then add a contingency for the unknowns. Check the total against what similar jobs have paid before you send the quote. The method below works for plumbers, electricians, builders and most other trades.

By the TradiesMate team · Facts checked 7 November 2026 · General information, not tax advice

How do you work out your day rate?

Your day rate has to cover more than the wage you want. Work it out once a year:

  1. Decide your target yearly pay before tax.
  2. Add your yearly overheads: van, fuel, insurance, tools, phone, software, accountant, training and certifications, and trade body fees.
  3. Count your billable days. Take 52 weeks, remove holidays, bank holidays, likely sick days, and the days spent quoting, buying materials and doing admin. Many trades find they bill far fewer days than they work.
  4. Divide (pay + overheads) by billable days. That's your break-even day rate.
  5. Add your profit margin on top, so the business can save, replace tools and survive quiet months.

If the rate looks high, check the billable days. That's usually where people fool themselves. One lime plasterer on r/Plastering worked out they'd spent "2 and a bit weeks" of a year quoting, writing estimates, invoicing and emailing, none of it paid, and now builds that time into their day rate (r/Plastering, June 2026).

How do you price a specific job?

  1. Break the job into tasks. For example: isolate, strip out, first fix, second fix, test, make good, clear up.
  2. Estimate hours for each task. Use your past jobs. If you don't track time, start now.
  3. Multiply by your hourly or day rate. Round up to half days if travel and set-up eat into the day.
  4. List the materials with current prices from your merchant. Prices move, so don't use last year's list.
  5. Add a materials markup to cover collection time, waste, returns and the cash you tie up.
  6. Add extras: skip, parking, permits, specialist hire, waste disposal and certification fees.
  7. Add a contingency for genuine unknowns, such as what's behind a wall. On older properties, say clearly what the contingency covers, or price it as a separate item.
  8. Add VAT if you're VAT registered.

What does a worked example look like?

Replacing a bathroom basin and taps, made-up figures for illustration only:

ItemWorkingAmount
Labour3.5 hours at £45 an hour£157.50
MaterialsBasin, taps, waste, fittings at cost £140, plus 15%£161.00
DisposalOld basin to the tip£10.00
ContingencySeized isolation valves£20.00
Total£348.50

Your own rates and markups will differ. The point is to show each line so you can see what makes up the price.

Should you charge by the hour or a fixed price?

Fixed price suits jobs you can see clearly. Customers like knowing the cost, and if you work fast, you earn more.

Day rate or hourly suits jobs with real unknowns, like fault-finding or old buildings. Say so in writing, give an estimate of the likely range, and agree to update the customer before going over it.

Many trades use both: a fixed price for the defined work, and a day rate for anything extra.

The trade-off comes up again and again. On r/DIYUK, one tradesperson said they give estimates rather than fixed quotes in the domestic market because "there are too many unforeseen variables": price for everything and you lose the job, price tight and the unknowns eat your margin (r/DIYUK, April 2026). Whichever you choose, say which one it is. Our guide to quote vs estimate covers the wording.

How do you check your price is right?

  • Compare with past jobs. Did similar ones make money?
  • Check what you'd earn per day on this job. If it's below your day rate, ask why.
  • Don't price to win at any cost. Cheapest isn't always what customers want. Clear quotes and quick replies win jobs too.
  • Review after the job. Note the actual hours and materials, and adjust next time.

What should you do after pricing?

Put it in a written quote with a clear scope, exclusions and a "valid until" date. Our guide on how to quote a job walks through the written quote, and the plumbing quote template and electrical quote template give you a layout to copy. If the customer goes quiet, use these quote follow-up texts.

How does VAT affect your prices?

If you're VAT registered, you charge VAT on your taxable work, and your quotes should make clear whether prices include it. GOV.UK says you must register if your total taxable turnover for the last 12 months goes over £90,000, or you expect it to go over £90,000 in the next 30 days (GOV.UK, when to register; VAT thresholds). The standard rate is 20%, with reduced and zero rates for some goods and services (GOV.UK, VAT rates). If you're getting close to the threshold, plan ahead: for domestic customers who can't reclaim VAT, adding 20% can make you look expensive overnight, so think about how your prices will change before you register. Speak to an accountant if you're unsure.

Key takeaways

  • Your day rate = (target pay + overheads) ÷ billable days, plus margin.
  • Break each job into tasks and estimate hours from past jobs.
  • Use current materials prices and add a markup for your time and cash.
  • Add a contingency for genuine unknowns and say what it covers.
  • Review actual hours after each job and adjust.

Questions

What markup should a tradesperson put on materials?

It varies by trade and job size. Set one that covers your collection time, waste and returns, and keep it consistent.

Should I show the customer my breakdown?

Show enough to make the quote clear: labour, materials and extras. You don't have to show your markup.

How do I price a job I've never done before?

Break it into tasks you have done, add time for learning, and consider a day rate with an estimated range instead of a fixed price.

Should I charge for travel?

Build normal travel into your rate. Charge separately for jobs well outside your usual area, and say so on the quote.

Sources

  • GOV.UK, When to register for VAT; VAT thresholds; VAT rates (checked 7 November 2026)
  • r/Plastering, "Let's talk about pricing" (June 2026) and r/DIYUK, "Tradesmen — how accurate are your quotes usually?" (April 2026), read 7 November 2026

TradiesMate keeps your rates and materials in a price book, so you can build a quote from your phone and text it to the customer to accept. Covered is £19.50 for your first 30 days, then £39 every 30 days with 250 texts. Try TradiesMate Covered.

Last checked 7 November 2026.

This page is general information, not legal, tax, financial or safety advice. We check our pages, but rules and products change and mistakes can slip through, so check anything important with a qualified professional or the official guidance before you act.

See how it works →

Questions this guide doesn't answer? Ask other UK tradespeople in the TradiesMate Community.

Quote faster from your phone

Covered is half price for your first 30 days. Money back if you ask within 30 days of your first payment.

Covered is £19.50 for your first 30 days, then £39 every 30 days with 250 texts. Minimum is £24. Cancel any time.